Difference between revisions of "Improve Electrics"

From Freeside Atlanta
Jump to navigation Jump to search
Line 1: Line 1:


* Projects
<big>Projects</big>
** Electrical
* Electrical
Next Step:   
:* Next Step:   
- [ ] Clarify steps required to get a project approved for work by others.
::* [ ] Clarify steps required to get a project approved for work by others.


As an example, what steps are required by Freeside in order to have work done that will make the kiln usable by members or guests?
As an example, what steps are required by Freeside in order to have work done that will make the kiln usable by members or guests?
Line 10: Line 10:
Punch List
Punch List


*** In
:::* In
**** run code electrical to light in kitchen
::::* run code electrical to light in kitchen
**** Run electrical to Form1 room
::::* Run electrical to Form1 room
**** Run electrical to kiln
::::* Run electrical to kiln
Per Scott, " Pretty sure it's split phase 240.  Pretty sure it just needs a 50A split phase outlet to run on 208V at a lower temperature/ramp."
:::::* Per Scott, " Pretty sure it's split phase 240.  Pretty sure it just needs a 50A split phase outlet to run on 208V at a lower temperature/ramp."
**** hole in outlet above projector
::::* hole in outlet above projector
**** inspect for exposed outlets
::::* inspect for exposed outlets
**** install lights in hallway
::::* install lights in hallway
*** Considering
:::* Considering
**** run electrical to outlets on wall between work tables and admin closet
::::* run electrical to outlets on wall between work tables and admin closet
**** Remove dropped quads from above work tables in front
::::* Remove dropped quads from above work tables in front
**** replace removed dropped quads above work tables with outlets at wall for each table
::::* replace removed dropped quads above work tables with outlets at wall for each table
**** 120v cables to quads in workshop
::::* 120v cables to quads in workshop
**** 240v to front left corner of auto bay
::::* 240v to front left corner of auto bay
**** 240v to large air compressor
::::* 240v to large air compressor
**** 240v to welding table
::::* 240v to welding table


*** Electricians Contacted:
:::* Electricians Contacted:
 
::::* Greg Pica of Socket Doctors
**** Greg Pica of Socket Doctors


[[Media:socket_doctor.jpg|business card]]
[[Media:socket_doctor.jpg|business card]]


No document (quote or estimate) received yet. (27 September)
:::::* No document (quote or estimate) received yet. (27 September)


**** Twon of AG Electrical LLC
::::* Twon of AG Electrical LLC


Phone: +1-470-301-7696
:::::* Phone: +1-470-301-7696


[[Media:Screenshot_20160928-151459.png|Estimate Document]]
[[Media:Screenshot_20160928-151459.png|Estimate Document]]

Revision as of 13:34, 29 September 2016

Projects

  • Electrical
  • Next Step:
  • [ ] Clarify steps required to get a project approved for work by others.

As an example, what steps are required by Freeside in order to have work done that will make the kiln usable by members or guests?


Punch List

  • In
  • run code electrical to light in kitchen
  • Run electrical to Form1 room
  • Run electrical to kiln
  • Per Scott, " Pretty sure it's split phase 240. Pretty sure it just needs a 50A split phase outlet to run on 208V at a lower temperature/ramp."
  • hole in outlet above projector
  • inspect for exposed outlets
  • install lights in hallway
  • Considering
  • run electrical to outlets on wall between work tables and admin closet
  • Remove dropped quads from above work tables in front
  • replace removed dropped quads above work tables with outlets at wall for each table
  • 120v cables to quads in workshop
  • 240v to front left corner of auto bay
  • 240v to large air compressor
  • 240v to welding table
  • Electricians Contacted:
  • Greg Pica of Socket Doctors

business card

  • No document (quote or estimate) received yet. (27 September)
  • Twon of AG Electrical LLC
  • Phone: +1-470-301-7696

Estimate Document